News & Research: Client Successes
Case Study: Integration of Transmission System Operations
ScottMadden managed the integration of two energy transmission system operations organizations.
- The client needed assistance integrating the energy transmission system operations functions of two companies it owned
- The client committed to full operational control of the new assets within six months of purchase
- A single energy management system (EMS) was to be used to manage the combined transmission assets
- Significant work in the field needed to be completed to enable operational control of the assets
- Worked with the client to develop future-state goals to be accomplished by closing and at final operational integration
- Developed a work plan to meet the key dates committed by management
- Tracked the work plan on a weekly basis. Emphasized the EMS integration and coordination with the field work
- Participated in biweekly management meetings on the status of the corporate integration
- The integrated company took operational control of the acquired assets on schedule
- All systems and field work required for operation was completed